NVER construction continues.

NVER construction continues.

Active work continues at the NVER construction site according to plan.

Right now, the foundation of the 2nd section is being laid and waterproofing works for the 3rd are being carried out, namely:

⁃ concrete mix laying for the 2nd section of the foundation has been completed;

⁃ the process of reinforcement and formwork installation for the foundation slab of the 3rd section is in progress;

⁃ concrete preparation work for waterproofing for the 3rd section is underway, which ensures reliable moisture resistance;

⁃ waterproofing works are continuing on the 3rd section to ensure the durability and stability of the building structures.

September 16, 2024

© All rights reserved. NVER, 2024.